In the Technology and Construction Court
Before: HHJ Stephen Davies sitting as a High Court Judge
Judgment delivered 28 May 2026
The facts
On 27 May 2020, Belong entered into a Pre-Construction Services Agreement with Seddon. The PCSA included the Proposed Contract Documents, primarily comprising an amended JCT Standard Building Contract (with Quantities) 2016 edition, that it was intended would be executed once the pre-construction services were completed.
In the PCSA:
- Clause 2.1 provided that the parties’ obligations would continue up to the earlier of the execution of the JCT contract or termination of the PCSA.
- Clause 2.2 provided that prior to execution of the JCT contract, the parties’ rights and obligations would be governed by the terms of the PCSA, supplemented by the Proposed Contract Documents.