Bennett contracted to Verbus the design, supply and installation of 78 prefabricated modular bedroom units for a new hotel in London.

United KingdomReal Estate and Construction

In the recent case of Bennett (Construction) Limited v CIMC MBS Limited (formerly Verbus Systems Limited)1 the Court of Appeal considered whether milestone payments in a construction contract constituted an adequate mechanism for payment in terms of the Housing Grants, Construction and Regeneration Act 1996, as amended ("the Act"). Martin Ewen explains more.

The facts

Bennett contracted to Verbus the design, supply and installation of 78 prefabricated modular bedroom units for a new hotel in London. The units were to be made in China and then shipped to Southampton. The contract price was just over £2 million. The contractual terms incorporated the standard form JCT contract. However, the standard JCT provisions for interim payments were deleted in their entirety and replaced by five bespoke "Milestone" provisions:

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from