Although the decision on the residential occupier point was sufficient to deal with RBH's attempt to enforce the adjudicator's decision...

United KingdomReal Estate and Construction

Although the decision on the residential occupier point was sufficient to deal with RBH's attempt to enforce the adjudicator's decision, Coulson LJ went on to consider the issues relating to the pay less notice. Once again, the judge summarised the relevant principles:

  1. What matters is not how the recipient of the notice in fact understood it; the question is how a reasonable recipient would have understood the notice.
  2. The notice must be construed in context. In other words, the reasonable recipient will be credited with knowledge of the relevant contract. If the notice in question is a pay less notice, the recipient will be taken to know the detail of its own payment notice, to which the pay less notice is a response.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from