It is not unusual for a design and build construction contract to contain a requirement to exercise reasonable skill and care in design alongside an absolute obligation to achieve a particular result.

United KingdomReal Estate and Construction

It is not unusual for a design and build construction contract to contain a requirement to exercise reasonable skill and care in design alongside an absolute obligation to achieve a particular result. In the absence of clear drafting, a tension may arise between the two obligations.

This is demonstrated by the recent Court of Appeal decision in MT Højgaard v E.On1.  We have previously written about the TCC's decision in the case, where the Court found that an absolute obligation effectively 'trumped' the requirement to exercise reasonable skill and care.  However, this decision has now been reversed by the Court of Appeal.

Whilst the Court of Appeal's approach to solving this tension will provide some comfort to designers, the decision serves as a timely reminder about the need for clearly drafted agreements.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.