The introduction of new standardised contract wordings goes a
long way towards providing the clarity required by underwriters in
evaluating the risks of decommissioning oil fields.
Global spend on decommissioning is reportedly estimated by Wood
Mackenzie to be USD85bn1 during the next decade.
Decommissioning on this scale will undoubtedly give rise to
multi-million dollar losses, often with no means of recouping these
losses following the end of a field's producing life. The
current slump in the oil price will further increase the need for
operators to keep their decommissioning costs to an absolute
minimum, passing on any unforeseen costs to insurers wherever
possible.
Anyone underwriting the risks associated with a decommissioning
project needs to understand the typical risk allocation between the
operator and contractors. The introduction in 2019 of a standard
form BIMCO contract (DISMANTLECON) followed the 2018 LOGIC
conditions. These standardised contract