Ofgem’s Proposed Data Centre Connection Reforms: A Significant Cost To Play And Stay

Browne Jacobson LLP
Browne Jacobson LLP
Contributor
Browne Jacobson LLP

Browne Jacobson LLP

We’re Browne Jacobson. The law firm for positive impact across business and society. Social and...

View firm profile
Explore more from Browne Jacobson LLP

The Office of Gas and Electricity Markets (Ofgem) recently published its ‘Curate – Demand Connections Reform’ consultation, setting out proposals to reshape how data centre projects access and hold positions in the UK's electricity grid connection queue.

United KingdomEnergy and Natural Resources

The Office of Gas and Electricity Markets (Ofgem) recently published its ‘Curate – Demand Connections Reform’ consultation, setting out proposals to reshape how data centre projects access and hold positions in the UK's electricity grid connection queue.

Ahead of the consultation deadline on 16 September 2026, here are my thoughts and insights for anyone with interests in data centre development, infrastructure finance, real estate or energy supply.

The problem Ofgem is tackling

The rapid growth of AI and cloud computing is driving unprecedented demand for data centre grid connections across the UK. According to Ofgem, the connection queue tripled between November 2024 and June 2025, from 41 GW to 125 GW, with approximately 315 data centres accounting for 3 GW of that surge, well above the UK's 2025 peak demand of 45 GW. The scale of this connection gap makes clear that significant speculation is already embedded in the queue, and recent reports of the National Energy System

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from