High Court Refuses Permission To Challenge Rejection Of Late Application Under Regulatory Scheme

Herbert Smith Freehills Kramer LLP
Herbert Smith Freehills Kramer LLP
Contributor
Herbert Smith Freehills Kramer LLP

Herbert Smith Freehills Kramer LLP

We have one of the largest Southeast Asia international law practices, working across the region...

View firm profile
Explore more from Herbert Smith Freehills Kramer LLP

The High Court has shown how strictly deadlines set by regulators can be enforced in Intelligent Land Investments Group PLC v Gas and Electricity Markets Authority [2026] EWHC 336 (Admin).

United KingdomEnergy and Natural Resources

The High Court has shown how strictly deadlines set by regulators can be enforced in Intelligent Land Investments Group PLC v Gas and Electricity Markets Authority [2026] EWHC 336 (Admin). In this case, Intelligent Land Investments Group PLC (ILIG) was refused permission for judicial review to challenge the Office of Gas and Electricity Markets (Ofgem)'s rejection of its application to the government's Long Duration Energy Storage (LDES) cap and floor scheme (the Scheme) following late submission of material.

Key points 

  • If a regulated entity misses a deadline to submit material, even if this was caused by an innocent clerical error, there is no guarantee that they will be able to submit the missing material after the deadline. 

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from