ESO Proposes The Retrospective Application Of The 'First Ready, First Connected' Approach For GB Grid

Osborne Clarke LLP
Osborne Clarke LLP
Contributor
Osborne Clarke LLP

Osborne Clarke LLP

About us Osborne Clarke is an international, full service law firm 1, headquartered in London. We...

View firm profile
Explore more from Osborne Clarke LLP

It is almost universally acknowledged that in Great Britain (as in many other European jurisdictions) grid connection delays are now the biggest barrier to the country achieving net-zero.

United KingdomEnergy and Natural Resources

It is almost universally acknowledged that in Great Britain (as in many other European jurisdictions) grid connection delays are now the biggest barrier to the country achieving net-zero.

In recent years, the connections queue has been growing at an exponential rate, with average delays of over five years for projects applying to connect to the transmission system. Ofgem expects the total queue size to rise to 800GW by the end of 2024, which is quadruple the amount of electricity generation that the UK is predicted to need by 2050.

The problem has become so acute in recent years that many developers are now seeing more value in developing projects outside Britain. Meanwhile, projects that are ready and waiting to connect have little prospect of doing so sooner than their prescribed date – and some projects are understood to have been offered the chance to bring forward their connection date by just one year if they accept a curtailment factor of over 90%.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from