Ofgem has published a consultation proposing to let developers, generators, storage operators and demand customers build their own connection assets all the way to the existing transmission system, rather than relying on a Transmission Owner to do it, and then hand those assets over once built. The current rule confining this option to sites within 2km of the grid, long seen as the main constraint on self-build, would be scrapped. Responses are due by 13 November 2026.
What has been proposed
Self-build and transfer (also called contestable build, or contestability) lets a connecting customer construct the assets linking its site to the transmission network itself, then transfer ownership to the relevant Transmission Owner (National Grid Electricity Transmission, Scottish Hydro Electric Transmission or SP Energy Networks) under an Adoption Agreement. Today that option exists only where the site sits within 2km of the existing network, or the assets are not potentially shareable.