Triple Point: More Than Simply ‘Liquidated Damages'

Fenwick Elliott LLP
Fenwick Elliott LLP
Contributor
Fenwick Elliott LLP

Fenwick Elliott LLP

Fenwick Elliott provides a comprehensive range of legal services on every aspect of the...

View firm profile
Explore more from Fenwick Elliott LLP

The Supreme Court judgment in Triple Point has perhaps received the most coverage in relation to the findings concerning liquidated damages.

United KingdomCorporate/Commercial Law

The Supreme Court judgment in Triple Point has perhaps received the most coverage in relation to the findings concerning liquidated damages. However, two other issues were considered by the Supreme Court in this important case, as explained in more detail by Karen Gidwani.

Summary of the case

By a contract dated 8 February 2013 ("the Contract"), PTT Public Company Ltd ("PTT"), a commodities trading company, engaged Triple Point Technology Inc ("Triple Point") to provide it with a Commodities Trading Risk Management and Vessel Chartering System ("CTRM system"). The works were to be carried out in two phases, and payment was to be made against milestones.

Article 5 of the Contract provided that, if Triple Point failed to deliver the work within the time specified and the delay was not caused by PTT, then Triple Point was liable for liquidated damages at the rate of 0.1% of "undelivered work per day of delay from the due date for delivery up to the date PTT

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from