The Supreme Court judgment in Triple Point has perhaps
received the most coverage in relation to the findings concerning
liquidated damages. However, two other issues were considered by
the Supreme Court in this important case, as explained in more
detail by Karen Gidwani.
Summary of the case
By a contract dated 8 February 2013 ("the Contract"),
PTT Public Company Ltd ("PTT"), a commodities trading
company, engaged Triple Point Technology Inc ("Triple
Point") to provide it with a Commodities Trading Risk
Management and Vessel Chartering System ("CTRM system").
The works were to be carried out in two phases, and payment was to
be made against milestones.
Article 5 of the Contract provided that, if Triple Point failed
to deliver the work within the time specified and the delay was not
caused by PTT, then Triple Point was liable for liquidated damages
at the rate of 0.1% of "undelivered work per day of delay
from the due date for delivery up to the date PTT