The Technology and Construction Court has ruled on a complex dispute between Vivergo Fuels and a contractor, Redhall Engineering Solutions.

United KingdomCorporate/Commercial Law

The Technology and Construction Court ("TCC") has ruled on a complex dispute between Vivergo Fuels (the "employer") and a contractor, Redhall Engineering Solutions, engaged by it to carry out mechanical and piping works on an engineering project.

The agreement between the two parties contained a two-stage termination procedure under which the employer: (i) notified the contractor of "material" breach and then; (ii) gave the contractor fourteen days to "commence and diligently pursue" rectification of the breach. (Perhaps this dispute could have been avoided if this clause had been drafted with more certainty by, for example, allowing the contractor a specified period in which to rectify the default rather than to "commence and diligently pursue" rectification.) 