No Room For Uncertainty: Final Date For Payment Must Be Tied To The Due Date

Wedlake Bell LLP
Wedlake Bell LLP
Contributor
Wedlake Bell LLP

Wedlake Bell LLP

Wedlake Bell provides clients with a full package of legal services delivering commercial and...

View firm profile
Explore more from Wedlake Bell LLP

A Technology and Construction Court ruling has found that payment clauses allowing the final date for payment to shift based on invoice submission timing violate the Housing Grants, Construction and Regeneration Act 1996. The decision resulted in the Scheme for Construction Contracts replacing the contractual payment terms, shortening the payment period from 30 to 17 days and invalidating the employer's pay less notices.

United KingdomReal Estate and Construction

A recent Technology and Construction Court (TCC) decision is a timely reminder of the need to ensure that payment clauses in construction contracts are compliant with the Housing Grants, Construction and Regeneration Act 1996 (“Construction Act”). 

In Deerns UK Limited v VDC LHR11 Limited [2026] EWHC 1509 (TCC), a consultancy agreement that allowed for the final date for payment to be postponed if the consultant issued an invoice later than the application for payment was found to be non-compliant. As a result, the contractual 30 days payment timetable was replaced by the Scheme for Construction Contract (“Scheme”), shortening the payment period to 17 days and making the Employer’s pay less notices ineffective. 

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.