Introduction
In December 2017 FIDIC released its second edition of the
Conditions of Contracts for Plant and Design Build ("the 2017
Yellow Book"), the Conditions of Contract for Construction
(the "2017 Red Book") and the Conditions of Contract for
EPC/Turnkey (the "Silver Book"), together the "2017
Contracts". As expected, FIDIC has made substantial amendments
to the dispute resolution provisions from the 1999 Red, Yellow, and
Silver Books (together the "1999 Contracts"), and it has
addressed the provisions relating to "binding but
not-final" Dispute Adjudication Board ("DAB")
decisions which have been the cause of persistent dispute since the
1999 Contracts were released.
However, rather than scale back following the controversy caused
by the binding but not-final DAB decision, and the severe
consequences to contractors that have in many instances resulted,
FIDIC has chosen to affirm this direction. The 2017 Contracts
therefore retain the same core structure of