In the Technology and Construction Court
Before the Honourable Mr Justice Pepperall
Judgment delivered 26 August 2026
The facts
For the purposes of undertaking works to expand the UK fibre optic data networks on behalf of its customer Nexfibre, Virgin retained contractors under framework agreements. Following Nexfibre’s publication of its anticipated volume of installations, Virgin entered into negotiations with its framework contractors to provisionally allocate the anticipated work.
On 7 May 2019, Virgin entered into a framework agreement with NMCN plc. Two further framework agreements with NMCN were completed on 14 February 2020 but during October 2021, NMCN entered administration and the framework agreements were novated to Svella. All the agreements included mutual rights of termination for convenience.