Share on LinkedInShare on LinkedIn

ARTICLE · 27 APRIL 2011

No Right To Terminate For Failure Of Condition

Charles Russell Speechlys LLP
Charles Russell Speechlys LLP
Contributor
Charles Russell Speechlys LLP

Charles Russell Speechlys LLP

Charles Russell Speechlys is an international law firm with a focus on private capital, at the...

View firm profile
Explore more from Charles Russell Speechlys LLP

Extra Services was to construct a hotel and lease it to Accor. Under the agreement, there was a condition that Extra Services should obtain, before a certain date, various consents relating to the development and other matters in order for the project to proceed.

United KingdomCorporate/Commercial Law

Extra MSA Services Cobham & Another v Accor UK & Others [2010] EWHC 775 (Ch)

Extra Services was to construct a hotel and lease it to Accor. Under the agreement, there was a condition that Extra Services should obtain, before a certain date, various consents relating to the development and other matters in order for the project to proceed. Extra Services was under an obligation to use all reasonable endeavours to satisfy the condition. If the condition was not satisfied by the specified date, either party could serve a notice to terminate. Extra Services duly did so when the date passed without the condition being satisfied. Accor challenged the effectiveness of the notice on the grounds that Extra Services had failed to use all reasonable endeavours as required by the agreement. Extra Services contended that the right to terminate was not conditional on property performance of its obligations to satisfy the condition.