Limitation Clause In Business Contract Not Unreasonable

Charles Russell Speechlys LLP
Charles Russell Speechlys LLP
Contributor
Charles Russell Speechlys LLP

Charles Russell Speechlys LLP

Charles Russell Speechlys is an international law firm with a focus on private capital, at the...

View firm profile
Explore more from Charles Russell Speechlys LLP

Elvanite claimed against AMEC, its professional consultant, for breach of contract. AMEC had been engaged to submit planning permission on a site for Elvanite by a stated date for a fee of about £14,000.

United KingdomCorporate/Commercial Law

Elvanite Full Circle Limited v AMEC Earth & Environmental (UK) Ltd [2013] EWHC 1191

Elvanite claimed against AMEC, its professional consultant, for breach of contract. AMEC had been engaged to submit planning permission on a site for Elvanite by a stated date for a fee of about £14,000. That did not happen. Elvanite agreed, subject to contract, to sell the site to a third party conditional on planning permission and an environmental permit. When planning permission did not come through by the expected date, the property market had turned and the buyer pulled out. Elvanite sought to recover its loss of profit on the deal from AMEC, alleging breach of contract. The agreement between them stated that: