Under the 2017 edition of the FIDIC Rainbow Suite, clause 19
which was headed "force majeure" has been replaced by
clause 18, "exceptional events". This is an interesting
change; the term "force majeure" is typically provided
for within most civil codes, whereas it is not a term of art under
the common law.
The essential scheme of the FIDIC Form has remained unchanged,
namely for something to amount to an exceptional event, there must
be an event which is beyond the control of the party affected and
which the party affected could neither have foreseen or provided
against before entering into the contract nor avoided once it had
arisen. The event must also not be the fault of the other party.
Under sub-clause 18.2 of the new second edition, the Contractor
must give a Notice, in the proper form, within 14 days of becoming
aware, or of the date when it should have become aware, of the
exceptional event. Subject to this, under sub-cause 18.3, the
Contractor may be