The shipyard, AAD, had agreed to build two ships for SMS. It was running very late with the construction. The contracts entitled SMS to rescind if the ships were not ready for sea trials on a given date and included a mechanism for awarding extensions if the purchaser made changes or there was a force majeure event.

United KingdomCorporate/Commercial Law

Adyard Abu Dhabi v SD Marine Services [2011] EWHC 848

The shipyard, AAD, had agreed to build two ships for SMS. It was running very late with the construction. The contracts entitled SMS to rescind if the ships were not ready for sea trials on a given date and included a mechanism for awarding extensions if the purchaser made changes or there was a force majeure event. AAD did not deliver the ships by the agreed date, so SMS rescinded and claimed for return of monies paid. AAD claimed that the "prevention principle" applied, namely that SMS was not entitled to insist on strict adherence to the time as SMS had caused the delay and in the alternative it claimed that AAD was entitled to an extension of time under the contract.