Breach Of Contract: Unforeseen Circumstances And Termination

Charles Russell Speechlys LLP
Charles Russell Speechlys LLP
Contributor
Charles Russell Speechlys LLP

Charles Russell Speechlys LLP

Charles Russell Speechlys is an international law firm with a focus on private capital, at the...

View firm profile
Explore more from Charles Russell Speechlys LLP

In the case of Burntcopper Ltd (t/a Contemporary Design Unit) v International Travel Catering Association Ltd [2014] EWHC 148 (Comm), the High Court has held that a clause that excused a party's performance of a contract due to unforeseen circumstances did not apply where that party sold the subject matter of the contract and the sale was forseen.

United KingdomCorporate/Commercial Law

In the case of Burntcopper Ltd (t/a Contemporary Design Unit) v International Travel Catering Association Ltd [2014] EWHC 148 (Comm), the High Court has held that a clause that excused a party's performance of a contract due to unforeseen circumstances did not apply where that party sold the subject matter of the contract and the sale was forseen. The Court also refused to imply a term that the contract could be terminated on reasonable notice.

Background

Burntcopper Ltd ("BCL") entered into a five-year fixed-term contract to provide International Travel Catering Association Ltd ("ITC") with exhibition management services for ITC's annual trade show. The contract contained, at the suggestion of ITC, a clause providing that it would not be enforced if, for some unforeseen circumstances, the trade show was cancelled or did not take place. BCL was unaware that ITC had been in preliminary discussions about selling the trade show to a third party.