This case shows the importance of stating that negotiations are "subject to contract" if it is the intention that they are not to form a binding contract.

United KingdomCorporate/Commercial Law

Malcolm Newbury v Sun Microsystems [2013] EWHC 2180 (QB)

Newbury was claiming sales commission from Sun Microsystems. A few days before the matter was due to come to trial, Sun's solicitors wrote to Newbury's solicitors saying that Sun "was willing to settle the entire proceedings by paying the Claimant within 14 days of accepting this offer, the sum of [ ]..... by way of damages by means of an electronic transfer..... in full and final settlement of the Claim and counterclaim,...... such settlement to be recorded in a suitably worded agreement." The offer was stated to be open until the end of the day. Newbury's solicitors responded the same day accepting the terms of the settlement in an email marked "Without prejudice save as to costs". They said that they would forward a draft agreement for approval the next day. A dispute then arose as to whether the terms of the settlement should be put onto the public record, with the result that no formal agreement was

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.