SLB & Others v PAK & Others [2026] EWHC 449 (Comm)
The question
Did an obligation, in a commercial shipbuilding contract, to provide refund guarantees within 120 days amount to a contractual condition, such that breach by failing to provide the refund guarantees entitled the buyers to terminate the contract and claim loss of bargain damages?
The key takeaway
Use of a stipulated time period, including the wording “by no later than 120 days,” might not, without more, be enough to make a term a condition, breach of which would give rise to common law loss of bargain damages. Here, an absence of clear wording, a lack of interdependence of obligations (this was a technical breach in nature) and an express contractual termination clause all pointed to the obligation to provide the refund guarantees within 120 days being an innominate term.