The Supreme Court examined whether a contractor could terminate a construction contract following two late payments by the employer, even though the first payment was made within the contractual cure period. The case centered on interpreting standard JCT contract termination provisions and whether a 'repeated default' clause required an earlier accrued right to terminate.

United KingdomLitigation, Mediation & Arbitration

Providence Building Services Limited v Hexagon Housing Association Limited [2026] UKSC 1

The question

Was a contractor’s right to terminate under a standard contract only triggered where the prior occurrence of the specified default gave rise to an entitlement to terminate?

The key takeaway

Absent clear wording, the courts are reluctant to construe termination rights (particularly in a standard contract) in such a manner that allows a party to end a high value contract upon minor breach(es). Where termination rights are drafted separately for each party, the court will not automatically assume they are intended to mirror each other, even where they adopt broadly similar structures.

The background

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.