This publication considers the recent case of Ener-G Holdings Plc v Hormell [2012] EWCA Civ 1059.

United KingdomCorporate/Commercial Law
Matt McCahearty
Matt McCahearty

This publication considers the recent case of Ener-G Holdings Plc v Hormell [2012] EWCA Civ 1059. The key issue in the case was whether the claimant had complied with a requirement, under a share purchase agreement, to issue proceedings for breach of warranty within 12 months of notifying the defendant of its claim. Clauses of this nature are not unusual in commercial contracts and, as this case shows, failure to comply with them is likely to result in a claim being time-barred.

BACKGROUND FACTS

By an agreement dated 2 April 2008 (the Agreement), the defendant sold shares in a company to the claimant. Under the terms of the Agreement, the claimant was required to notify the defendant of any claim for breach of warranty no later than the second anniversary of the date of completion (i.e. by 2 April 2010) and to issue proceedings within 12 months of providing such notice. Failure to comply with this obligation would result in the claim being "deemed to have been