In the recent case of SMBT v Hollard Insurance and Others, the Gauteng division of the High Court dealt with the proper interpretation of a guarantee...

South AfricaInsurance

In the recent case of SMBT v Hollard Insurance and Others, the Gauteng division of the High Court dealt with the proper interpretation of a guarantee, namely; whether a guarantee issued by the guarantor to make payment in the event of default by the principal debtor had expired, by the time a demand under the guarantee was delivered.

Background

On 20 March 2015, SMBT concluded a written building agreement ("the Agreement") with Cape Island Construction ("CIC") to build a new dwelling on its registered immoveable property situated in Kloof Road, Clifton, Cape Town for the contract price of ZAR42 795 598. In conjunction with this Agreement, SMBT was issued a 'variable construction guarantee' ("the Guarantee") in its favour by Hollard Insurance Company to pay if CIC defaulted.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from