1. INTRODUCTION
A three-judge bench of the Hon'ble Supreme Court of India
(the "Court") recently passed a judgment
dated 11th November 20211 (the "said
Judgement") dealing with various afflicting practices
of the promoters and builders, and further clarified the existing
inconsistencies within various provisions of the Real Estate
(Regulation and Development) Act, 2016 ("the
Act").
2. BACKGROUND
A complaint was instituted by the homebuyers and allottees
before the Uttar Pradesh Real Estate Regulatory Authority (the
"Authority") for refund of their
investment amount along with interest under Section 31 of the Act
as the promoters had failed to hand over the possession of the
units to the allottees in accordance with the home buyers'
agreements.