Recently, vide its order, Hon'ble Maharashtra Real Estate Appellate Tribunal ("MREAT") in the case of Dilip J Mehta ("Complainant/Allottee") vs. Akshar Developers ("Promoter") & Ors...

IndiaReal Estate and Construction

1. INTRODUCTION

Recently, vide its order, Hon'ble Maharashtra Real Estate Appellate Tribunal ("MREAT") in the case of Dilip J Mehta ("Complainant/Allottee") vs. Akshar Developers ("Promoter") & Ors.1 directed the Promoter to deliver possession of alternative units in lieu of units already booked of equal area at the already agreed price of total consideration as per the allotment letter dated August 09, 2006, after adjusting the payments already made and adjustment of interest accrued in favour of Complainant.

2. FACTS

Complainant booked two units being unit nos.67 and 68 admeasuring approximately of 4090 sq. ft. each ("said Units") in Akshar Decorum Business Park- phase I ("said Project") being developed by the Promoter for a consideration of Rs. 59,30,500 per unit. No agreement for sale was executed between the Complainant and Promoter. According to clause 14 of the allotment letter dated August 09, 2006 issued by the Promoter ("Allotment Letter"),

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from