The Supreme Court, vide its judgment dated February 20, 2026 in Parsvnath Developers Ltd. v. Mohit Khirbat (Civil Appeal No. 5289 of 2022 and connected matters)...

IndiaReal Estate and Construction

Overview:

The Supreme Court, vide its judgment dated February 20, 2026 in Parsvnath Developers Ltd. v. Mohit Khirbat (Civil Appeal No. 5289 of 2022 and connected matters), dismissed a batch of appeals filed by the developer challenging orders of the National Consumer Disputes Redressal Commission (NCDRC). The Court affirmed the NCDRC's directions for time-bound completion of construction and payment of compensation at 8% simple interest per annum for delays in delivering flats. The ruling emphasizes the remedial nature of consumer protection laws.

Brief Background and Facts:

The appeals stemmed from consumer complaints filed before the NCDRC by homebuyers who had booked residential flats in the Parsvnath Exotica project between 2007 and 2011. Under the Flat Buyer Agreements, possession was to be delivered within 36 months from the commencement of construction, with a six-month grace period. Despite the buyers paying nearly the entire sale consideration,