ARTICLE · 28 MAY 2020

Highlights Of The Advisory On Extension Of Timelines Under RERA

On May 13, 2020, the Ministry of Housing and Urban Affairs issued an advisory to the state governments to invoke the Force Majeure clause under the provisions of the Real Estate...

IndiaReal Estate and Construction

1. INTRODUCTION

1.1 On May 13, 2020, the Ministry of Housing and Urban Affairs (the "Ministry") issued an advisory to the state governments to invoke the Force Majeure clause under the provisions of the Real Estate (Regulation and Development) Act, 2016 ("RERA") and to extend the timelines for (i) completion of the real estate projects which has been delayed due to pandemic caused by Covid-19 and (ii) for various statutory compliances ("RERA Advisory") under the provisions of RERA. As per the RERA Advisory, the Ministry mulled and considered the effect of the ongoing pandemic situation which resulted in reverse migration of the workers to their native places and break in supply chain of the construction material causing an adverse impact on the construction activities of real estate projects across India.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from