A recent order of the Haryana Real Estate Appellate Tribunal serves as a compelling reminder that the right to seek appellate redress under the Real Estate (Regulation and Development) Act, 2016 (“RERA”)...

IndiaReal Estate and Construction

Introduction

A recent order of the Haryana Real Estate Appellate Tribunal serves as a compelling reminder that the right to seek appellate redress under the Real Estate (Regulation and Development) Act, 2016 (“RERA”) is neither unconditional nor inexhaustible. In dismissing an application for condonation of a staggering delay of 487 days in the filing of an appeal, the Tribunal has reinforced the primacy of limitation law and the indispensable obligation of litigants to exercise their remedies with reasonable promptness and due diligence.

Background and Factual Matrix

The appellants, Pankaj Chawla and another, had invested in Unit/Shop No. 0059, admeasuring a super area of 552 sq. ft., situated within the commercial project “Amb Selfie Street” at Sector 92, Gurugram, developed by the respondent, Amb Infraventures Pvt. Ltd. An order was passed against the appellants by the Haryana Real Estate Regulatory Authority, Gurugram (“Authority”) on 03 January 2024.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from