ARTICLE · 02 OCTOBER 2020

The Supreme Court Of India Clarifies The Law On Limitation For Enforcement/Execution Of A Foreign Awards Under Section 47 Of The Arbitration Act And Jurisdiction Of The Enforcement Court In Such Proceedings:

Parinam Law Associates
Parinam Law Associates
Contributor

Parinam Law Associates

Parinam Law Associates is a multi-specialty law firm with offices in Mumbai, New Delhi and Pune....

View firm profile
Explore more from Parinam Law Associates

Divergent views have been taken by some High Courts with respect to the period of limitation for filing a petition for enforcement of a foreign award and the procedure applicable for enforcement/execution ...

IndiaLitigation, Mediation & Arbitration

Divergent views have been taken by some High Courts with respect to the period of limitation for filing a petition for enforcement of a foreign award and the procedure applicable for enforcement/execution of foreign awards under the Arbitration and Conciliation Act, 1996 ("Arbitration Act"). A three judge bench of the Supreme Court recently clarified the issue in Government of India v. Vedanta Limited and Ors.1

I. FACTS:

In 1994 the Government of India had executed a Product Sharing Contract ("PSC") to develop the Ravva Oil and Gas Field with the Respondents. The contract scheme was such that the Respondents could recover the costs incurred for petroleum operations from the Government. Disputes had arisen on the interpretation of Article 15.5 of the contract which pertains to development costs.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from