Divergent views have been taken by some High Courts with respect
to the period of limitation for filing a petition for enforcement
of a foreign award and the procedure applicable for
enforcement/execution of foreign awards under the Arbitration and
Conciliation Act, 1996 ("Arbitration
Act"). A three judge bench of the
Supreme Court recently clarified the issue in
Government of India v. Vedanta Limited and
Ors.1
I. FACTS:
In 1994 the Government of India had executed a Product Sharing
Contract ("PSC") to develop the Ravva
Oil and Gas Field with the Respondents. The contract scheme was
such that the Respondents could recover the costs incurred for
petroleum operations from the Government. Disputes had arisen on
the interpretation of Article 15.5 of the contract which pertains
to development costs.