Share on LinkedInShare on LinkedIn

ARTICLE · 22 FEBRUARY 2018

Supreme Court Holds That Enforcement Of An Award Through Its Execution Can Be Filed Anywhere In The Country Where Such Decree Can Be Executed

Shardul Amarchand Mangaldas & Co
Shardul Amarchand Mangaldas & Co
Contributor
Shardul Amarchand Mangaldas & Co

Shardul Amarchand Mangaldas & Co

Founded on a century of legal achievements, Shardul Amarchand Mangaldas & Co (SAM & Co) was born...

View firm profile
Explore more from Shardul Amarchand Mangaldas & Co

In disputes between Sundaram Finance Limited ("Appellant") and Abdul Samad in relation to default in repayment of a loan, an ex-parte arbitration award was made on 22 October 2011 in favour of the Appellant ("Award").

IndiaLitigation, Mediation & Arbitration

Brief Facts

In disputes between Sundaram Finance Limited ("Appellant") and Abdul Samad in relation to default in repayment of a loan, an ex-parte arbitration award was made on 22 October 2011 in favour of the Appellant ("Award"). The Award being enforceable as a decree under Section 36 of the Arbitration and Conciliation Act ("Act"), the Appellant filed execution proceedings before the Court at Morena, Madhya Pradesh under Section 47 read with Section 151 and Order 21 Rule 27 of the Code of Civil Procedure, 1908 ("CPC"). The Court vide order dated 20 March 2014 ("Order") returned the execution application on account of lack of jurisdiction to be presented to the Court of competent jurisdiction. While passing the Order, the Court relied upon a decision of the Madhya Pradesh High Court on this issue. The effect of the Order was that the Appellant was required to file the execution proceedings first before the Court of competent jurisdiction in Tamil Nadu, obtain a