ARTICLE · 06 JULY 2021

SC's Order On Laying Underground Power Transmission Lines In GIB Habitats In Gujarat And Rajasthan

The Supreme Court of India ("SC") has recently passed an order relating to laying of power transmission lines in the states of Rajasthan and Gujarat, in an environmental public interest litigation.

IndiaLitigation, Mediation & Arbitration

The Supreme Court of India ("SC") has recently passed an order relating to laying of power transmission lines in the states of Rajasthan and Gujarat, in an environmental public interest litigation.

A group of environmentalists in 2019 had filed a writ petition in the nature of public interest in the SC, to seek protection and conservation of the Great Indian Bustard ("GIB") species. It was contended that GIBs are on the verge of extinction due to their death caused by collision and/or electrocution with the overhead power transmission lines and wind turbines.

After hearing arguments of both the sides, the SC had passed an order on April 19th, 2021 ("SC Order") directing the relevant authorities of the Rajasthan and Gujarat government to (i) install all future power lines as underground power lines and (ii) convert all existing overhead power lines to underground power lines, subject to feasibility (as indicated in the below flowchart), in the priority and potential

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from