Non-Signatories To Arbitration Agreement Beyond The Group Companies Can Also Be Included In The Arbitration Based On Contractual Links: Delhi High Court

In a recent decision, in RBCL Piletech Infra v. Bholasingh Jaiprakash Construction Limited1 the High Court of Delhi ("High Court") decided a petition ("Petition")...

IndiaLitigation, Mediation & Arbitration

In a recent decision, in RBCL Piletech Infra v. Bholasingh Jaiprakash Construction Limited1 the High Court of Delhi ("High Court") decided a petition ("Petition") under Section 11(6) of the Arbitration and Conciliation Act, 1996 ("Arbitration Act"). By way of the Petition, the petitioner sought the initiation of arbitral proceedings against two entities that were neither signatory to the arbitral agreement nor group companies of the signatory company. This article delves into the facts of the matter, and findings of the High Court.

Brief Facts

The disputes, as per the petitioner, arose in the context of a work order dated 4 April 2022 ("Work Order"). The second respondent, National Thermal Power Corporation ("NTPC"), is the owner of a site where certain project works were being undertaken by Bharat Heavy Electrical Ltd. ("BHEL"). BHEL, in turn, sub-contracted part of the works to the first respondent ("BJCL"). BJCL ultimately sub-contracted a portion of its