Interference At The Referral Stage In Section 11 Proceedings Under The Arbitration Act Permissible Only When The Claims Are Manifestly Time Barred: Calcutta High Court

In a recent ruling, the Calcutta High Court, in Kalpataru Projects International Limited v. Bharat Heavy Electricals Limited (BHEL) [AP-COM No. 94 of 2025], appointed an independent arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996 ("A&C Act").

IndiaLitigation, Mediation & Arbitration

Introduction

In a recent ruling, the Calcutta High Court, in Kalpataru Projects International Limited v. Bharat Heavy Electricals Limited (BHEL) [AP-COM No. 94 of 2025], appointed an independent arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996 ("A&C Act").

The High Court rejected BHEL's objections regarding limitation and non-joinder of parties, holding that the Petitioner's claims were not ex facie time-barred and that issues concerning the consortium agreement should be decided by the arbitral tribunal. In this article, we navigate through the facts of the case and the findings rendered by the High Court.

Brief Facts

The dispute arose from a Work Order issued to the predecessor-in-interest of Kalpataru Projects International Limited ("Petitioner"). The predecessor company had formed a consortium with Simplex Projects Limited to execute a project for BHEL. Subsequently, following a merger, Kalpataru took over the obligations of