In Steel Authority of India Ltd. v. H. R. Construction Pvt. Ltd., [C.O. 4004 of 2024] the Calcutta High Court dismissed a civil revision petition challenging an interim award by an arbitral tribunal allowing amendment of claims at an advanced stage of the proceedings.

IndiaLitigation, Mediation & Arbitration

Introduction

In Steel Authority of India Ltd. v. H. R. Construction Pvt. Ltd., [C.O. 4004 of 2024] the Calcutta High Court dismissed a civil revision petition challenging an interim award by an arbitral tribunal allowing amendment of claims at an advanced stage of the proceedings. The High Court held that the tribunal had acted within its discretion under Section 23(3) of the Arbitration and Conciliation Act, 1996 ("Arbitration Act") and found no irregularity in the order permitting the amendment.

The petitioner, Steel Authority of India Ltd. (SAIL), had objected to the amendment on the ground that it was sought at the stage of final arguments and would result in delay and prejudice. The arbitral tribunal had nevertheless permitted the amendment, imposed costs on the claimant, and granted liberty to the respondent to file additional pleadings. The High Court affirmed this approach, holding that the amendments did not alter the nature or character of the original

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from