Since the enactment of the Insolvency and Bankruptcy Code in
2016 (“IBC, 2016), the judiciary has been very active in
settling disputes and addressing the gaps arising from this
controversial legislation. Recently, yet another dispute arising
out of a technical gap in the IBC has been resolved by the Apex
Court in the case of M/s Consolidated Construction Consortium
Limited v. M/s Hitro Energy Solutions Private
Limited1.
Brief facts of the case
An agreement for a new project was entered into between Chennai
Metro Rail Limited (“CMRL”) and M/s
Consolidated Construction Consortium Limited
(“Appellant/ “Operational Creditor”). For the
purpose of supplying light fittings, on June 24, 2013, the
Appellant had placed orders with Hitro Energy Solutions
(“Proprietary Concern”/ “Respondent”). The
Proprietary Concern requested an advance payment of INR 50,00,000/-
(Fifty Lakhs) and a cheque for the said amount was issued by CMRL
in favour of the Proprietary Concern.