The National Company Law Tribunal ("NCLT"), granted a
60-day extension on February 13, 2024 for the resolution process of
the grounded airline Go First. Thisextension was followed based on
the admission of a plea by the Resolution Professional of Go First,
requesting additional time to complete the corporateinsolvency
resolution process ("CIRP") [NCLT order IA/592/2024].
The NCLT previously granted a 90-day extension, ending on
February 4, 2024 forthe completion of the airline's insolvency
resolution process under the Insolvency & Bankruptcy Code
("IBC"). The IBC mandates that the CIRP must be finalized
within 330 days, including litigation periods, or the corporate
debtor faces liquidation. Go First voluntarily initiated insolvency
proceedings on May 10, 2023 ceasing operations on May 3, 2023.
However, they opted to restart the resolution process to allow