Third Amendment To The GNA Regulations – Key Highlights

AZB & Partners
AZB & Partners
Contributor
AZB & Partners

AZB & Partners

AZB & Partners, one of India’s premier law firms was founded in 2004 with a clear purpose to...

View firm profile
Explore more from AZB & Partners

The Central Electricity Regulatory Commission ("CERC") issued the CERC (Connectivity and General Network Access to the Inter-State Transmission System) Regulations, 2022...

IndiaEnergy and Natural Resources

The Central Electricity Regulatory Commission ("CERC") issued the CERC (Connectivity and General Network Access to the Inter-State Transmission System) Regulations, 2022 on June 7, 2022 ("GNA Regulations"), with the objective of enabling non-discriminatory open access to the inter-State transmission system ("ISTS") for generating companies through the general network access ("GNA") framework. The GNA Regulations were subsequently amended on April 1, 2023 and June 19, 2024.

On August 31, 2025, the CERC issued the third amendment to the GNA Regulations ("Third Amendment"), introducing significant changes to the procedures involved in the grant of connectivity, its withdrawal and relinquishment, the key conditions for grant of connectivity and GNA, change of control restrictions, etc.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from