Supreme Court Upholds Recovery Of Transmission Charges For Power Grid’s LILO Assets

In Power Grid Corporation of India Limited v. Tamil Nadu Generation and Distribution Corporation Limited, 2026 SCC OnLine SC 2445, the Supreme Court clarified that transmission charges may be recovered where transmission assets have been commissioned and put to use, even if the wider transmission network is not fully operational.

IndiaEnergy and Natural Resources

In Power Grid Corporation of India Limited v. Tamil Nadu Generation and Distribution Corporation Limited, 2026 SCC OnLine SC 2445, the Supreme Court clarified that transmission charges may be recovered where transmission assets have been commissioned and put to use, even if the wider transmission network is not fully operational.

The Supreme Court, comprising Justice J.B. Pardiwala and Justice K. Vinod Chandran, allowed the appeals filed by Power Grid Corporation of India Limited (PGCIL) and restored the order passed by the Central Electricity Regulatory Commission (CERC). The Court held that PGCIL was entitled to recover transmission charges for two Line-In Line-Out (LILO) arrangements at the Tuticorin Pooling Station, notwithstanding the delay in commissioning the dedicated transmission line (DTL) by the generating company.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from