The Central Electricity Authority (“CEA”), through notification dated 22.06.2026, has issued the Central Electricity Authority (Technical Standards for Construction of Electrical Plants and Electric Lines) Amendment Regulations, 2026 (“Amendment Regulations”)1, thereby amending the CEA (Technical Standards for Construction of Electrical Plants and Electric Lines) Regulations, 2022 (“Principal Regulations”). The amendment inserts a new Chapter VI prescribing, dedicated construction standards for solar, floating solar, onshore wind, offshore wind, and Battery Energy Storage System (“BESS”) installations. The key highlights of the amendments are as follows:
The common requirements for Renewable Energy Power Plants (“REP”) and BESS include equipment rating norms, mandatory site documentation, display boards, WMO-compliant automatic weather stations (for plants of 10 MW and above), phasor measurement units, harmonic analysers, power plant controllers, redundant communication systems,