Claims Which Are Not A Part Of The Resolution Plan Shall Stand Extinguished On The Date Of Approval Of The Resolution Plan By The Adjudicating Authority

Argus Partners
Argus Partners
Contributor
Argus Partners

Argus Partners

Argus Partners is a leading Indian law firm with offices in Mumbai, Delhi, Bengaluru, and Kolkata....

View firm profile
Explore more from Argus Partners

On April 18, 2023, the National Company Law Appellate Tribunal, New Delhi ("NCLAT") gave its decision in the case of Ashvinkumar Jayantilal Patel v. Shri Sanjay Jitendralal Shah...

IndiaCorporate/Commercial Law

On April 18, 2023, the National Company Law Appellate Tribunal, New Delhi ("NCLAT") gave its decision in the case of Ashvinkumar Jayantilal Patel v. Shri Sanjay Jitendralal Shah, whereby it has held that a resolution plan providing for carrying forward of liabilities of the Corporate Debtor toward the suspended directors, post CIRP, is non-compliant with Section 31(1), IBC, which mandates that all claims which are not a part of the resolution plan, shall stand extinguished on the date of approval of the resolution plan by the Adjudicating Authority. Thus, the NCLAT upheld the Adjudicating Authority's decisions to reject the resolution plan on the above grounds.

Brief Facts:

B&C Energy Infra Limited ("Corporate Debtor"), a Micro, Small & Medium Enterprise ("MSME") unit, was admitted into corporate insolvency resolution process ("CIRP") on January 3, 2022. Subsequent to receiving and verifying of claims, the resolution professional of the Corporate Debtor ("RP")

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from