ARTICLE · 29 MAY 2019

Jurisdiction Of Consumer Forums Not Barred By Rera But Rather Only Power To Grant Injunction Taken Away By Express Provision Of Section 79 Of Rera Act, 2016 – NCDRC New Delhi

King, Stubb & Kasiva
King, Stubb & Kasiva
Contributor
King, Stubb & Kasiva

King, Stubb & Kasiva

King Stubb & Kasiva is few of the top corporate law firms in India with offices in Bengaluru,...

View firm profile
Explore more from King, Stubb & Kasiva

The Complainant Ajay Nagpal had purchased a flat in the said project whereas delivery of possession was not handed over to the Complainant.

IndiaConsumer Protection

INTRODUCTION

After the introduction of the RERA (Real Estate Regulation and Development) Act, 2016 (hereinafter referred to as "RERA") adjudication of real estate matters whether registered or non-registered with the RERA were categorically held to fall within the scope of the Act as per the judgment in the case of Simmi Sikka v. M/s Emmar MGF Land Limited[1]. The order of HARERA (Haryana Real Estate Regulatory Authority) clarified that the projects registered previously with the Director of Town and Country Planning (hereinafter referred to as "DTCP") before commencement of the Act can be adjudicated by RERA. In the present case the developer M/s. Today Homes and Infrastructure Pvt. Ltd. (hereinafter referred to as "developer") registered the project titled as "Canary Greens"[2] with the DTCP, Haryana. The Complainant Ajay Nagpal had purchased a flat in the said project whereas delivery of possession was not handed over to the Complainant. The Complainant filed

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

https://ksandk.com/

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from