1. Key takeaways
Extension of time periods requires balancing the
interests of the parties, the court, and the public (R. 9.3(a)
RoP)
Extensions are granted only in justified exceptional
circumstances to ensure efficient proceedings. The court considers
whether the requested extension will jeopardize the preparation of
the oral hearing (reason 2.c)).
In this case, the Defendants' request for a three-week
extension was granted due to new technical arguments raised by the
Claimant involving third-party software and a security environment.
The court found the Defendants' need for additional time to
consult with a third-party developer and a private expert
plausible.
The Court expressly mentions that all other circumstances
invoked by Defendants (holidays, unavailability of the private
expert for one week due to a conference) are not decisive for an
extension of a time period.