1. Key takeaways
Order of a confidentiality regime step-by-step from
uploading the document to the decision and any requests for access
to the file
The regime reflects the interest – typically arising from
the provision in license agreements that the contract may only be
produced upon a court order – that the respective licence
agreement partner shall be involved into the proceedings and its
confidentiality regime prior to any production in the court
proceedings. The regime makes an order under Rule 190 RoP
unnecessary for the time being.
Typically, there is a recognisable need for
confidentiality of business-related information contained in
licence agreements.
If an order under Rule 190 RoP is not appropriate for
the time being, any documents to be produced can be submitted by
means of Rule 9 RoP in conjunction with Rules 262/262A
RoP.