LD Düsseldorf, November 20, 2024, Request For Extension Of Time Limits, UPC_CFI_499/2023

Bardehle Pagenberg
Bardehle Pagenberg
Contributor
Bardehle Pagenberg

Bardehle Pagenberg

IP practitioners with technical expertise As one of Europe’s leading IP law firms, BARDEHLE...

View firm profile
Explore more from Bardehle Pagenberg

Defendants have not consented to the extension of the time limits. However, the requested extension is justified on the grounds of fairness and equity (see the 5th recital in the Preamble to the Rules of Procedure)...

GermanyIntellectual Property

1. Key takeaways

Fairness and Equity regarding Extension of Time Limits

Defendants have not consented to the extension of the time limits. However, the requested extension is justified on the grounds of fairness and equity (see the 5th recital in the Preamble to the Rules of Procedure), since the previous time limit was, with the consent of the Claimant, extended to a similar extent in favour of the Defendants.

2. Division

LD Düsseldorf

3. UPC number

UPC_CFI_499/2023

4. Type of proceedings

Patent infringement action and Counterclaim for revocation

5. Parties

Claimant: DexCom, Inc.

Defendants:

  1. Abbott Laboratories
  2. Abbott Diabetes Care Inc.
  3. Abbott GmbH

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from