1. Key takeaways
Foreseeable professional commitments and school holidays do not amount to “exceptional circumstances” under R. 9.3(a) RoP
Representatives before the Court are expected to organise their professional activities and make appropriate arrangements within their legal teams so as to ensure compliance with procedural time periods.
A heavy workload resulting from other pending cases does not, in itself, justify an extension, particularly where the competing professional commitments were foreseeable. The applications do not establish that the matters identified could not have been addressed through appropriate advance planning, allocation of work or other reasonable organisational measures. This applies all the more to commitements that fall after the expiry of the time period for which extension is sought.