The CoA partially overturned a broad evidence production order of the LD Copenhagen and clarified the limits on the scope. The Court of First Instance had ordered Appellant to produce, subject to a penalty payment of up to EUR 1,000 per day of delay, complete construction drawings, manuals and “other materials” provided to customers.
Appellant appealed, raising five grounds: disproportionality, lack of evidentiary necessity for process features, fishing expedition / pre-emptive remedies, self-incrimination, and insufficient confidentiality measures.
The Court of Appeal partially upheld the appeal. It confirmed that a production order was justified in principle, given that the claimant had presented plausible evidence of infringement and the relevant technical information lay exclusively within the defendant’s sphere of control. However, the scope of the order was excessive in three respects: