The Court of King's Bench of Alberta has provided important new guidance regarding construction lien timelines. The registration of a construction lien and certificate of lis pendens (CLP) is an effective way of securing payment for labour, materials or services provided on a construction project. To ensure that lien claims are determined in a timely manner, section 46(2) of the Prompt Payment and Construction Lien Act, RSA 2000, c P-26.4 (the PPCLA) provides that, if a trial has not been held within 2 years from the date of registration of a CLP, an interested party may apply to the Court to have the lien and CLP discharged.
However, a party may elect to deposit security with the Court to stand in place of the lands and clear the lien and CLP from the applicable land title. In these circumstances, does the 2-year limit in the PPCLA still apply? In 1951789 Alberta Ltd v Britannia Block General Partnership Inc, 2026 ABKB 283 (Britannia Block),the Court confirmed that it does not.