The Ontario Court of Appeal has ruled that construction lenders cannot automatically reduce posted lien security simply by making direct payments to subcontractors. This decision creates potential funding shortfalls for lenders who advance money to keep trades working while existing lien security remains tied up.

CanadaReal Estate and Construction

In Demikon Construction Ltd. v. Oakleigh Holdings Inc., 2026 ONCA 808, released November 10, the Ontario Court of Appeal confirmed that paying subcontractors directly does not automatically reduce security posted to remove a general contractor’s lien from title.

The owner sought to reduce its posted security by approximately $3.55 million in direct trade payments. The Court dismissed the appeal because the evidence did not establish which trades still had valid lien rights when paid. A reduction required proof of those rights and compliance with the statutory direct-payment requirements. 

For construction lenders, the risk is a funding shortfall. Meaning, money advanced to keep trades working may leave the existing lien security tied up.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from